<aside> <img src="https://img.icons8.com/ios/4x/info.png" alt="https://img.icons8.com/ios/4x/info.png" width="40px" /> SCENARIO John, Jack and Frank are each assigned a task for a project. Frank should not start working on his task until John and Jack’s tasks are complete.

HOW

  1. Frank’s task is related to the upstream tasks to create a connection
  2. The “Wait” checkbox is ticked to indicate that the upstream tasks should be completed first
  3. The “Show” checkbox will automatically be ticked when the upstream tasks are completed
  4. In a filtered view for Frank, show only tasks with the “Show” checkbox checked

</aside>

Users

Tasks